Snow Hill, Birmingham
You are here: Snow Hill, Birmingham
  • Name: Snow Hill, Birmingham
  • Category:
  • Client: HEDF 11 Birmingham S.a.r.l
  • Description:
We were appointed Principal Contractor to carry out the demolition of this multi storey tower block and 5* hotel situated in the Snow Hill area at the heart of Birmingham City Centre.

Our scope of works included the removal of all site vegetation, the demolition of the cores and numerous kicker walls back to podium level together with the demolition of the advertising hoarding block and the subsequent protection of the site by the provision of a secure timber hoarding complete with lighting.

Given the confines of the site we deployed specialised equipment to carry out the top down deconstruction of the towers including our 100Tn Telescopic Crawler Crane with hydraulic driven munching attachments and our 1200Tn long reach mechanical d-rig with a reach of 65 meters.

Prior to demolition works commencing, we undertook considerable structural modifications to the part completed superstructure to ready the development for an alternative use as instructed by our client.

The project was delivered safely and on time